1. What is this item?
This is the main grid hookup for your farm—installing a service pole (or extending one) from the nearest power line and fitting the utility meter. It’s your gateway to powering pumps, lights, workshops, and any future solar or backup systems.
2. How is the Quantity Estimated?
• Number of Poles: Usually 1 pole per connection—more if you’re >100 m from the main line.
• Cable Length: Distance from pole to your switchgear or control room (measured in meters).
• Meter Type: Single-phase vs. three-phase depends on load estimate (e.g., pumps, workshop machinery).
3. Cost Components
• Utility Connection Fee: Application + service deposit charged by the electricity board.
• Pole Supply & Erection: Concrete/steel pole, foundation, hardware.
• Meter & Meter Box: Standard or smart meter, wiring, protective enclosure.
• Service Cable & Wiring: Underground or overhead cabling from pole to farm’s switchgear.
• Installation Labor: Licensed electrician + lineman charges.
• Documentation & Inspection: Approvals, site inspection fees.
4. Going Rates & Per Unit Cost**
• Connection Fee: ₹5,000–₹15,000 (varies by state board).
• Pole (30 ft) + Erection: ₹18,000–₹30,000 per pole.
• Meter & Box: ₹2,500–₹5,000.
• Service Cable: ₹150–₹300 per meter.
• Installation Labor & Testing: ₹5,000–₹10,000.
Example: For a 50 m run to a three-phase meter:
• Pole & erection: ₹25,000
• Meter setup: ₹4,000
• Cable (50 m × ₹200): ₹10,000
• Labor & fees: ₹8,000
Total ≈ ₹47,000 (₹940/m including pole)
🔌 Grid power on farm = peace of mind—powering everything from pumps to party lights!